Renovation, Collaroy NSW
Collaroy: Rewiring a Five-Bedroom Home Mid-Renovation
A cosmetic renovation turned into a full electrical overhaul once the walls came open. Builders changed and the design kept moving for six months, and the electrical work caused no delays.
- Location
- Collaroy, Northern Beaches
- Timeline
- 6 months
- Property
- 5-bedroom home with pool
- Builders
- 2, coordinated on site
- Reset: old switchboard disconnected and temporary power set up for the builders
- Design: lighting and power laid out room by room with the clients and builder
- Rough-in: all cabling through wall frames and ceiling cavities, every run photographed
- Fit-off: switches, power points, downlights and external lighting, plus a late induction cooktop
- Handover: every circuit and safety switch tested, with full compliance documentation